Recently we do observe significant delays on rail corridors in Poland (up to 60 hrs for import and 40 hrs in export).
That is related to major rail network reconstructions in GPP (Gdansk North Port Station) and is beyond our direct control.
We expect reconstructions to end by end of August 2022.
Together with our partners we do our best to improve this complex situation.
Until then, we strongly suggest:
For import: Please plan delivery date for your containers (via Kąty Wrocławskie and Sławków terminal) no earlier than 7 calendar days from vessel ETA.
For export: No changes, we will do our best to deliver your containers to meet cargo cut off.
For further questions, we encourage you to liaise with your local Maersk Line customer service representative or check Maersk website.
We want to thank you for your business and look forward to continuously serving your global transportation needs.
Related articles
See all newsAnything you need, we’re here to help
Logistics solutions
Contact us
Ready to ship?
By submitting this form, I agree to receive logistics related news and marketing updates from A. P. Moller-Maersk and its affiliated companies via e-mail. I understand that I can opt out of such Maersk communications at any time. To see how we process your personal data, please see our Privacy Notification.